Mile End Hospital
Client : Tower Hamlets PCT Estimates and Facilities Department
Consultants: Mile End Hospital London E1 4DG
A very complicated installation to de-centralise the existing steam generating plant that required detailed complex planning to retain all existing heating, hot & cold water and gas services to this bed hospital that incorporates a day-care centre.
This involved the creation of 3 large independent LTHW plant rooms comprising of modular boilers and new flues, associated control panels linked to BMS, pumps, motorised valves etc.
The work was further complicated by asbestos removal and the fact that a number of services were almost untraceable. Before any removal, adaptation or interception could take place numerous investigative exercises had to be carried out to avoid inadvertent disruptions to the hospitals operations and careful programming where this was unavoidable.
In support of our works we had 3 large portable gas boilers and freezer based lorries working throughout this process. The entire contract was completed within 15 weeks.
Testimonial
"Mid Essex Heating (London) Ltd have carried out some difficult projects on our behalf during our association, keeping services operational whilst successfully carrying out major works. We have found them to offer a user friendly and flexible approach at competitive prices."
Roger Brooks - Facilities Manager Tower Hamlets PCT Estimates and Facilities Department