Jenny Hammond Primary School

Project Jenny Hammond Primary School
Location Worsley Road, Leytonstone, London
Client Forest Gate Construction
Start Date 26th May 2009
Completion Date August 2009, phased works
Value £20,567

The Jenny Hammond Primary School is an existing building; the works comprise of a 100m2 extension block to facilitate the new staff room, offices and reprographics and the refurbishment of part of the existing building.

The extension block accommodates new bathroom and kitchen facilities with services extended from the existing building. The refurbishment of the existing building includes the stripping out and installation of new W.C’s and tea stations in new locations and associated works in relocating facilities.

We are responsible for undertaking the mechanical installations; above ground drainage, below ground drainage, domestic hot and cold water, rainwater, gas servicing, heating and ventilation.

This is currently a live project.

Testimonial

"We have worked with MEH on various projects in recent years,

Including several major works where services were required to be kept operational throughout. Even on particularly difficult projects this has been achieved, all with a friendly and flexible approach

from all involved. The current project we envisage completion on time as usual"

Forest Gate Construction